Use of the safety function

Activating

1. Lock the POUS key switch. The switch locks in "ON" (open) position.

Resetting

1. Unlock the POUS switch until it releases.
2. Push the POUS reset button [S7x] (if installed). The indication lamp [P7x] goes out, the POUS
deactivates.
Note: You must push the reset button [S7x] for 0.1 to 3 seconds.
3. Reset the drive if necessary.
4. Make sure that the drive has received the start signal (depends on the configuration, see the
firmware manual).
5. You can now restart the drive.
Note: You have to reset the POUS circuit with the reset button [S7x] also after you have powered up the
drive.

POUS indications

When the POUS is on:
the drive control program has the warning Safe torque off active,
the POUS indication lamp [P7x] is illuminated,
the mode LED of the safety relay [A65] is steady blue.

+Q957 Fault tracing

This table describes the status LEDs of the emergency stop safety relay [A65].
CH1
Mode
off
off
green
green
flash
off
green
flash
off
green
flash
green
green
off
blue
off
blue
green
blue
green
blue
green
blue
CH2
Status
off
The safety relay is not powered.
CH1 and CH2 accepted. Reset made
green
and outputs activated.
CH1 and CH2 unaccepted. A timer
function is counting down while the
off
safety relay remains activated.
CH1 unaccepted and CH2 accepted.
A timer function is counting down
while the safety relay remains
green
activated.
CH1 accepted and CH2 unaccepted.
A timer function is counting down
while the safety relay remains
off
activated.
off
No channels accepted.
green
CH1 unaccepted, CH2 accepted
off
CH1 accepted, CH2 unaccepted
CH1 and CH2 accepted, the safety
green
relay waits for reset.
Two-channels error: CH2 has been
fast flash
unaccepted and then accepted
green
again while CH1 remained accepted.
3ADW000504R0301 +Q957 Prevention of unexpected start-up en c
Action
Check A1–A2 voltage and
connections.
Check CH1 and CH2
Check CH1
Check CH2
Check reset settings, wiring
and reset/test circuit
Check installation. Restore by
opening and closing both
CH:s at the same time.