Shipping and Handling

1. This actuator is shipped in the FULLY CW position (2 color position indicator
shows "CLOSE" and the Reference Dimple aligns with "0"). (The "1" mark is the
FULLY CCW position).
2. NOTE, THIS ACTUATOR MUST HAVE WATER TIGHT EMT FITTINGS, WITH
CONDUIT DRAINAGE INSTALLED AND POWER SUPPLIED TO UNIT TO
KEEP THE HEATER WARM AT THE TIME OF INSTALLATION.
3. Storage: This unit should NOT be stored outside unless it is powered up
and has proper conduit terminations. When NOT powered up, it should be
stored in a clean, dry environment at all times.
4. This actuator has been factory calibrated to operate between 0 degrees and
90 degrees. Most quarter-turn products will not require recalibration of
these settings. If any travel adjustment is necessary, please refer to pages 6-8
for instructions.

Product Mounting and Setup

1. Fully CLOSE the valve or damper to which the actuator is to be mounted.
Keep in mind this actuator rotates CW (as viewed from above the unit) when driving CLOSED.
2. Assemble necessary linkage components and attach the actuator to the driven device.
3. Tighten mounting bolts, making sure actuator is centered on the device drive shaft.
4. Utilize the handwheel to check for unobstructed manual operation from fully CCW to fully CW positions BEFORE
applying power to the unit.
5. Make the electrical connections per wiring diagram on page 4.
Connect POWER to terminals marked 1 and 2 on the switch card.
Actuator accepts any one of 4-20mA, 1-5vdc or 2-10vdc signal.
Connect CONTROL wires on the control card (DMC 102) to terminals marked J2T4 and J2T5. The positive wire
MUST connect to terminal marked J2T5 or the controller will not function.
The drain wire on the signal cables must be grounded at ONE END ONLY! (Preferably at the supply end).
6. Do NOT apply power at this time.
Installation Notes
These actuators are designed to be used between a horizontal and upright position. Do NOT mount the assembly with
the actuator top below a horizontal position.
When installing conduit, use proper techniques for entry into the actuator. Use drip loops to prevent conduit condensate
from entering the actuator.
Mechanical travel stops are factory calibrated for 90 degree operation. These stops are NOT designed to adjust
mechanical rotation by more than +/- 3 degrees, they are for positioning the handwheel only.
Both NPT conduit ports MUST use proper equipment to protect the NEMA 4X integrity of the housing.
The internal heater is to be used in ALL applications.
Do NOT install the actuator outdoors or in humid environments unless it is powered up and the heater is functioning.
Use proper wire size to prevent actuator failure (see chart on page 4 for proper wire sizing).
All terminals accept 12-16AWG solid/stranded wire.
Page 3 of 14 P2/3 12VDC Proportional Series
REFERENCE
DIMPLE
"0" = CW
"1" = CCW