Installation

2.1

Space Requirements

Installation plate thickness: 1.5 - 9.0 mm (0.06 - 0.35 inch)
Space requirements when installing the operator panel:
252 mm
(9.92 inch)
50 mm
(2.0 inch)
Caution:
The openings on the enclosure are for air convection. Do not cover these openings.
2.2

Installation Process

1. Unpack and check the delivery. If damage is found, notify the supplier.
Note:
Place the operator panel on a stable surface during installation.
Dropping it or letting it fall may cause damage.
Beijer Electronics, MAEN773F
100 mm
(4.0 inch)
50 mm
(2.0 inch)
100 mm
(4.0 inch)
382 mm
(15.04 inch)
Panel cut out
343 x 208 mm
(13.5 x 8.18 inch)
x 14
Installation
100 mm
(4.0 inch)
58 mm
(2.28 inch)
7

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the EXTER K100 and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents