5
Installing Cables
5.1
Connecting the Equipotential Ground Cable and Power Cable
1. When routing the cables, wrap the section of all signal cables inside the smart cooling
product with the corrugated pipes and route them out of the corresponding cable holes so
that the strong- and weak-current cables are separated.
2. Route the power cable along the rear door post, and use cable ties to secure the cable to the
post every 150–200 mm.
1. Connect the equipotential cable.
(Optional) Connecting the Water
5.2
Sensor
2. Connect the power cable.
Installing T/H Sensors Outside
5.3
Cabinets
1. Connect the temperature and humidity
(T/H) sensor cable.
T/H sensors in the aisle should be installed
at the door frame inside the server cabinet
and 1.5 m above the ground (33 U). After
they are secured, set the sensor positions
based on their location and the table.