REPLACEMENT INSTRUCTIONS | ACH580-01 VXR UL TYPE 1 , R1/R2
Step
Instruction
10
Using a T20 bit, loosen and remove two (2) M4x8 screws. Remove
conduit assembly.
Recycle the conduit assembly and hardware.
11
CAUTION! Use two people to install the drive.
Slide the drive mounting holes over the bottom two (2) screws and
slide drive in place.
Using a T30 bit, replace the two (2) M6 screws that were removed
earlier.
Torque all four (4) mounting screws to 27 in-lb (3 Nm).
Diagram