Summary of Contents for Jacto J-1000

  • Page 2 J-1000 is shipped in three crates 66” x 42” x 22” 506 lbs Notice each crate has Serial Number. When assembling multiple units insure to match insure to match SN’s on the crates. In the smaller crate the axle and tires can be found below the bumper.
  • Page 3 Step One: Attach front jack support and tires to the axle. . . Hoist the front of sprayer at the chassis. Attach the jack support to the front of the Attach the jack support to the front of the chassis using the pin and cotter key set provided with it.
  • Page 4 Step Two: Slide the crate bottom out and move the tires/axle in. . . Hoist the rear of sprayer at the chassis. Position the axle with tires into position Position the axle with tires into position under the sprayer. Place the spacer between the chassis and the axle.
  • Page 5 Step Three: Attach tongue and tank sump protective cover. . . Using the two long pin and cotter key sets. Attach the tongue to the bottom front of the sprayer. sprayer. Insert the rear pin first (as the hole is slotted). Using the four bolts, washers, and nuts provided secure the tank sump protective id d...
  • Page 6 Step Four: Attach draw bar and tie rod to tracking axle. . . Slide the draw bar into the tongue, Straighten up the tires. secure with washer, castle nut and Rotate the tie rod clockwise Rotate the tie rod clockwise cotter pin.
  • Page 7 Step Five: Prepare chemical hose. . . Remove the two wing nuts and washers (one on each side) and lift off front hood. ff f Unwrap all hoses and route them through the opening in the front of the hood. The black hose must be connected securely to the top/front of the pump.
  • Page 8 Step Six: Install the chemical control valve. . . Affix the Control Valve Mount to the front of the chassis using the two (2) front of the chassis using the two (2) bolts provided. Attach the Control Valve to the Attach the Control Valve to the mount using the two (2) bolts &...
  • Page 9 Step Six: Install the chemical control valve (continued). . . Attach the Blue (chemical Notice the lower bypass) hose to the upper port connection for Black connection for Black by pulling out the retainer, t th chemical hose from the pushing in hose connector and pump uses two (2) replacing retainer.
  • Page 10 Step Seven: Install PTO and drive shaft cover. . . Slide the PTO onto the drive shaft then secure with the nut and bolt. Then slide the drive shaft cover over the PTO. Secure the drive shaft cover in place using the two bolts provided in the th t b lt...
  • Page 11 Step Eight: Install fan guard and rear bumper. . . Fasten the fan guard into place th f d i t using the bolts provided. Secure the rear bumper using the four bolts Two on each side of the four bolts. Two on each side of the chassis.
  • Page 12 Step Nine: Assemble the Duct. . . Last attach the outlet duct using the long bolt going all the through Second attach the revolving duct Use 6 of the long bolt/nut sets. First attach the fixed duct, Use 8 of the bolt/nut sets, there will be two larger bolts to attach to the chassis (circled)