Boiler's Assembly Guidelines; Requirements For Boiler-Room - SAS MULTI Series Technical - Start - Up Documentation

Water boilers for heating installations
Table of Contents

Advertisement

In the "traditional combustion " mode:
black coal for energetic applications of size grade of nut coal (class 24/12 acc. to
PN-91/G-04510).
With water furnace, it is possible to apply with good results so called long flame
fuels, such as: brown coal and wood in different forms, e.g. chips, silvers, shavings,
etc. The wood has to be seasoned at least one year!
Wet wood combustion lowers the efficiency and the lifetime of a boiler.
Boiler's assembling should be performed
(qualified person upon adequate training and authorized for performing maintenance
and repair works). The fitter's obligation is to get familiar with the product, its
functioning and protection systems functionality.
Prior to boiler's assembling it is strictly necessary to get familiarized with
the content of hereby Technical-Start-Up Documentation.
The boiler room, where the heating boiler for central heating installation shall be
installed, must conform the requirements of detailed regulations being in force, at the
country of destination (e.g. PN-87/B-02411).
In particular, the following requirements shall be fulfilled:
the boiler rooms should be located as centrally as possible to rooms
which are covered with heating system, and the boiler itself should be placed
as close as possible to chimney (chimneys),
boiler rooms entrance door should be opened on the outside, and be made of
inflammable materials,
the boiler room should have air blow-out ventilation, a channel with section no
less than 50% of the chimney section, but not less than 21 x 21 cm, with the exit
at the back part boiler's room, (lack of such ventilation or obstruction may cause:
smoking, inability to get higher temperature),
the boiler room should have blow- out ventilation under room's ceiling with
section no less than 25% of the chimney section, but not less than 14 x 14
cm (the purpose of this system is to carry out harmful gases).
NOTE: Employing of mechanical blow-out ventilation is unacceptable.
The boiler room should be provided with day and artificial lighting.
5. BOILER ASSEMBLY GUIDELINES

5.1. REQUIREMENTS FOR BOILER-ROOM

by qualified and authorized personnel
- 10 -