9 Dismantling and fitting with removed air inlet and gas outlet / 9.4

Removing the cartridge group with compressor and turbine casing

9.4
Removing the cartridge group with compressor
and turbine casing
Fig. 47: Turbine cleaning nozzle
1. If present: Loosen the turbine cleaning connection.
The cleaning nozzle (51301) must be replaced after each removal procedure. If the clean-
ing nozzle is not to be replaced, the screw connection (01) must not be loosened during
disassembly.
Fig. 48: Remove insulation
2. Remove the compressor casing insulation.
3. Remove the turbine casing insulation.