INSTALLATION PROCEDURES

3.3.1 GOODS INWARDS INSPECTION

RA-5J00 was factory tested, inspected, packed, and delivered to the carrier with utmost care. Do not
accept shipment from carrier which shows damage or shortage until the carrier's agent endorses a
statement of the irregularity on the face of the carrier's receipt. Without documentary evidence, a claim
cannot be processed.
Open and check each package against the packing list. For any shortage, contact Comba Telecom
Systems. Do not remove items from packing materials until installation.

3.3.2 TOOLS

See Appendix B for a full list of tools required for installation and maintenance.

3.3.3 PREPARATION

Optical Fiber:
Fiber optic cables require proper handling. Do not stretch, puncture, or crush the fiber cable(s) with
staples, heavy equipment, doors, etc.
Always maintain the minimum bending radius specified by the cable manufacturer. The minimum
bend radius is usually 10 times as the cable's outer diameter. In the case of single optical fiber that is
not in a cable, the minimum bending radius to be observed is 3cm.

3.3.4 MU CARBINET MOUNTING

ENU STATUS : 1-0-0
USER MANUAL FOR RA-5J00
Figure 9: MU Carbinet Mounting