Flow diagram
Burner control unit flow diagram
Phase
Display Description
Relay test
"P"
Fan ramp-up for test
Safety relay test
Disable relays BV1 and BV2.
Relays test BV1 and BV2
Ignition relay test
Disable safety relay.
Start-up meter, initialisation
Standby
"0"
Standby
Start-up
"1"
Flame signal amplifier test
Gas fan and air pressure switch test
"2"
Fan ramp-up
"3"
Pre-purge
Adjusting start-up load, test WD 1
"4"
Pre-ignition
"5"
Ignition safety time
Flame detection safety time
Operation
"6"
Flame stabilising time
"7"
Start-up, partial load
Modulating operation
Adjust shutdown load.
Shutdown
"8"
Reheat, test WD 2
Fan ramp-up, post-purge
Post-purge
Waiting
"U"
Waiting for restart
"C"
Waiting for mains gas pressure
Fault
"9"
Forced ventilation fault
states
"10"
Flame tear-off
"11"
Safety shutdown
"F"
Fault shutdown
30
(cont.)
Duration
max. 20 s
0.9 s
0.9 s
0.9 s
0.9 s
0.9 s
0.1 s
0 ... s
max. 50 s
max. 20 s
max. 20 s
10 s
1.9 s
2 s
2.3 s
max.
0.51 s
15 s
20 s
0 to 24 h
0.1 s
min. 10 s,
max. 60 s
max. 20 s
10 s
1 min
5 min
20 s
0 ... s
0 ... s
0 ... s