Installation Sequence; Installing The Gateway And Power Supply Unit - Viessmann WAGO MB/TCP gateway Installation And Service Instructions For Contractors

Bms communication with heating systems via modbus
Hide thumbs Also See for WAGO MB/TCP gateway:
Table of Contents

Advertisement

Process overview
Step
1
Install the gateway and power supply unit.
2
Establish the CAN bus connection.
3
Connect the plug-in attachment.
4
Establish the connection to the Modbus.
5
Connect the gateway to the power supply unit.
6
Power supply
7
Commission the gateway.

Installing the gateway and power supply unit

The gateway and power supply unit are suitable for
mounting on top-hat rails in control panels:
TS 35 to EN 50 022: 35 x 15 and 35 x 7.5.
!
Please note
Incorrect ambient conditions and installation
locations may impair data transfer and cause
damage to the gateway.
The gateway, together with its components, con-
stitutes an open device with IP 20 protection rat-
ing. It may only be installed in enclosures, cabi-
nets or in electrical plant rooms.
Ambient conditions during operation
Permissible ambient temperature: 0 to 40 °C
Permissible relative humidity:
0 to 39 °C:
95 %
40 °C:
50 %
No direct sunlight
Requirements for the enclosure
Material
Min. dimensions
(width x height x depth)
Protective conductor
Flammability class
Earthing
IP rating
Top-hat rail mounting
!
Sheet steel
200 x 200 x 120 mm
Connect the enclosure to the protec-
tive conductor.
Enclosure and top-hat rail:
Depending on phase conductor
cross-section with min. 2.5 mm
Installed at a height of up to 1.60 m: IP 20D
Installed at a height of 1.61 m or higher: IP 20B
TS 35 to EN 50022
Length: Min. 190 mm

Installation sequence

Responsibility
Contractor
Contractor
Contractor
IT expert/system integrator
Electrician
Electrician
IT expert/system integrator
Please note
Operation by unauthorised persons may result
in damage to the system.
Access to the gateway must only be possible for
authorised specialists with a key or tool.
Plastic
278 x 278 x 130 mm
Connect the top-hat rail to the protec-
tive conductor via a protective conduc-
tor terminal.
Min. flammability class V-1 according
to EN 62368-1 or EN 60950-1
Top-hat rail:
Depending on phase conductor cross-
2
section with min. 2.5 mm
Page
9
17
19
22
23
24
27
2
9

Advertisement

Table of Contents
loading

This manual is also suitable for:

Wago mb/rtu gateway

Table of Contents