Chapter 3. Installation

Pre-Installation

22
Perform the following steps prior to uncrating the system. It is a good
idea to have performed these steps prior to delivery of the system.
Note: If the seismic restraint is being installed, the
hospital must have identified the location of
the restraints and have pre-drilled the proper
holes.
1. Prior to your arrival, verify the number of cartons and items shipped
to the customer.
2. Confirm that a proper location exists for correct installation; the
location should be the correct size for the unit with the needed
amount of clearance in front and on the cassette access side if
necessary.
®