The 4-way Vertical Air Handling Unit is factory ready for vertical up or hor-
izontal left installation. Horizontal right installation requires field reconfigu-
ration of the indoor unit. The internal drain pan must be removed from the
left side of the unit and reinstalled on the right side. For horizontal right, no
additional parts are necessary.
This procedure describes how to convert the VAHU to horizontal right
configuration.
1. Remove the upper and lower front panels.
2. Remove the two panel supports and the refrigerant pipe support.
3. Remove the thermistor from the coil assembly.
4. Carefully remove the coil assembly and the drain pan.
5. Move the drain pan to the right (opposite) side of the coil assembly. Be
sure the drain connections are in the correct location to allow drain pipe
connection.
6. Carefully reinstall the coil assembly and drain pan.
7. Reinstall the coil assembly thermistor.
8. Reinstall the two panel supports and the refrigerant pipe support.
9. Reinstall the upper and lower front panels.
22
Due to our policy of continuous product innovation, some specifications may change without notification.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. "LG" is a registered trademark of LG Corp.
Figure 12: Remove Front Panel.
Figure 13: Remove Coil and Drain Pan.
Figure 14: Install Pan on Right.
Figure 15: Replace Panels.

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Lv241hv4Lv361hv4Lv420hvLv480hv

Table of Contents