To Convert The System For Use With A Different Type Of Gas; To Modify Settings For Gas Conversion; Commissioning; To Fill The Condensate Trap - Daikin D2CND028A1AB Installation Manual

Wall-mounted condensing boiler
Hide thumbs Also See for D2CND028A1AB:
Table of Contents

Advertisement

5 Commissioning

DANGER
Isolate the boiler from the power mains before gas
conversion operation.
INFORMATION
Only for Belgium
Gas conversion from Natural gas to propane gas can only
be executed by Daikin Belux Service Department. Please
contact Daikin Belux Service Department to organise an
appointment on site.
4.10.1
To convert the system for use with a
different type of gas
1 Open the front cover of the unit as described in this manual.
2 To set natural gas, adjust screw on the gas valve to position "1".
3 To set LPG, adjust the screw to position "2".
4 Mount the front cover, connect the unit to the main power
supply.
4.10.2

To modify settings for gas conversion

1 Enter the menu section from the user interface. Select service
settings by using the left dial.
2 Press the "Enter" button and choose the password (742) by
using the right dial and press the "Enter" button again.
3 Choose "C" parameters via left dial and press the "Enter"
button.
4 Choose "CE" and press the "Enter" button. It will ask for
password again. Choose the password (115) and press the
"Enter" button.
5 Choose "C0" and press the "Enter" button.
6 To convert to LPG, choose "1" with the right dial and press the
"Enter" button, To convert to Natural gas, choose "0" with the
right dial and press the "Enter" button.
7 Leave the menu screen and go back to the home screen by
using the "Back" button.
INFORMATION
When a conversion is performed, the identification label
shall be marked to show the gas type in use.
5
Commissioning
WARNING
Only qualified persons should conduct commissioning.
Installation manual
26
CAUTION
Preliminary electrical system checks such as earth
continuity, polarity, resistance to earth and short circuit
must be carried out by using a suitable test meter by a
competent person.
Especially for UK:
It is a requirement that the boiler is installed and commissioned to
the manufacturer's instructions and the data fields on the
commissioning checklist completed in full.
To instigate the boiler guarantee the boiler needs to be registered
with the manufacturer within one month of the installation.
To maintain the boiler guarantee it is essential that the boiler is
serviced annually by a Gas Safe registered engineer who has been
trained on the boiler installed. The service details should be
recorded on Service Interval Record and left with the householder.
5.1

To fill the condensate trap

INFORMATION
Water must be poured into the inner tube.
Fill the condensate trap by pouring 0.3 litres of water from the boiler
flue outlet.
5.2

Gas-air ratio: No need to adjust

The installer does not have to adjust the gas-air ratio, because the
boiler has an electronic gas adaptive feature.
5.3

To check for gas leakage

DANGER
Before passing next steps, this control must be fulfilled.
1 Before connecting the unit to power mains, close valves 1, 2
and 3.
2 Connect a manometer to gas counter.
3 Open valves 1, 2 and 3.
4 Close valve 1.
5 Note the manometer measurement and wait for 10 minutes.
6 After 10  minutes, compare the manometer measurement with
the initial value. If the pressure is decreased, it means there is
gas leakage. Check the gas line and fittings.
7 Repeat this process until being sure that there is no leakage.
8 Close valve 1, remove the manometer and open valve 1 again.
D2CND028+035A1/4AB + D2TND028+035A4AB
Wall-mounted condensing boiler
3P469346-5N – 2019.11

Advertisement

Table of Contents
loading

Table of Contents