4.

INSTALLATION

Firstly separate the two side plates and the central load bar. The Load Bar has a left
and right hand thread which is indicated by the letter "L" & "R" and the load bar end.
Start by screwing the left hand thread side of the load bar into the left sided side plate,
to start only screw approximately 5mm of thread into the side plate, repeat the same
for the right hand side plate. Once both side plates are secure proceed with turning the
Load bar until the thread is flush with the outer sides of both side plates.
The unit is now ready to attach it to the suitable beam. Final adjustment can now be
made so that the trolley fits correctly on the lower flange of the beam. The clearance
between the flange of the running wheel and the edge of the beam must not exceed
the following:-
Fitted With Standard Length Load Bar (A)
Capacity of Trolley
500-1000Kgs
2000Kgs
3000Kgs
5000Kgs
Fitted With Extended Length Load Bar (B)
Capacity of Trolley
500-1000Kgs
2000-3000Kgs
5000Kgs
NEVER increase the clearance to accommodate large curves
Clearance
Beam Width
1.5-3.0mm
50-220mm
1.5-3.0mm
66-220mm
1.5-3.0mm
74-220mm
1.5-3.0mm
90-220mm
Clearance
Beam Width
1.0-1.5mm
160-300mm
1.5-2.0mm
160-3000mm
2.0-2.5mm
160-300mm