Heater; Pressure Relay; Putting Into Operation - ABB UZE Installation And Commissioning Manual

On-load tap-changers with motor-drive mechanism, type buf 3
Hide thumbs Also See for UZE:
Table of Contents

Advertisement

9.3.5 Heater

Switch off all power supplies and feel by hand that the heater has been warmed up during
earlier tests. Switch on the power afterwards.
Check that the air vents are open.
Remove the drying agent used during transport.

9.3.6 Pressure relay

Check the function as per section 5.3.

9.4 Putting into operation

Put the LOCAL/REMOTE switch to REMOTE. Reset the drag hands.
Make sure that no tools or foreign objects are left in the motor drive cabinet. Close the door.
1ZSE 5492-115 en, Rev. 5
9 Commissioning
29