Setup (cont'd)
Loading Cable
1. Rotate the ground separator out and down.
2. Feed the cables over the lower traction wheel.
• Do not cross the cables.
• If pulling a smaller diameter ground cable, feed it
in at the leftmost side of the cable feeder.
Greenlee Tools, Inc.
6810-22 Ultra Cable Feeder
3. Lower or remount the upper drive unit by lifting up
on the catch located near the clevis pin on the
control box side of the unit while lowering the upper
drive unit.
4. Push down on the ratchet handle with a moderate
amount of force. Engage the catches.
5. Rotate the ground separator and cable divider into
place, if desired. If pulling more than five cables,
place two cables in one section of the cable divider.
Make sure the cable divider is fully seated against
the Stiff-arm Shaft.
Note: If pulling cable larger than 600 volt 1000 MCM,
do not use the cable divider.