9.Periodical checks:

!
9.1. General
During normal service, the circuit-breakers
are maintenance-free. The frequency and
sort of inspections basically depend on the
service conditions. Various factors must be
taken into account: frequency of 
operations, interrupted current values,
relative power factor and the installation
ambient.
9.2 Checking program
Checking operation
Carry out five mechanical
opening closing operations.
Visual inspection of the poles
(insulating parts).
Visual inspection of the operating
mechanism and transmission.
Measuring the insulation
resistance.
Before carrying out any operation, make sure that the operating
mechanism springs are discharged and that the apparatus is in
the open position.
RELATED TITLES
Power
ABB Motor
Transformers
Starting Br
As a precaution, the following
gives the checking program , s
the relevant time intervals. As
time interval between these o
is concerned, it is advisable to
with specifications given in the
least during the first check. On
of the results obtained during t
inspections, contact an ABB se
for any clarifications.
Time interval
1 Year
The circuit-breaker must
normally without stopping
intermediate positions
1 Yr./ 5000
The insulating parts must
operations
any accumulation of dust,
discharges or traces of surf
discharges
1 Yr./ 5000
The elements must be free
operations
deformation.
Screws, nuts, bolts, etc. mu
1 Yr/5000
operations
ABB Protection
Transform
ABB
Criteria
See par. 8.1. point 1.