Commissioning

• Start the EnergyHub by closing the breaker
• Wait for one minute for the display starts.
• Press and hold on the display until it says Service menu activated
• Sweep right and left to switch between different views.
• Sweep until you find the Table view, seen below, and verify that the system is inactive.
If not sweep to the Start and Stop menu and press Stop.
• Go the CT-ration view and insert the correct CT-ratio
• To change the CT ratio push on the number.