To Start-Up The Scf System - Carrier ChillerVu 23XRV Series Application Manual

Counterflow
Hide thumbs Also See for ChillerVu 23XRV Series:
Table of Contents

Advertisement

To start-up the SCF system

With the chillers set for CCN control, set the start command in the SCF program by accessing the i-Vu® interface
and navigating to Properties > Control Program tab > Run Conditions > Chiller Manager Start (BBV, BNI, or BBI,
depending on your system). Select Start or On, as applicable.
The Equipment Run Status should change to On and, after a short delay, the lead machine should enable and
ramp up.
Assuming sufficient load, the lag machine starts when:
The lead machine exceeds 79% capacity (in Chiller Lead/Lag Control, the Load of lead chiller default
value)
The chilled water supply temperature is greater than the setpoint for 10 minutes
When the lag machine starts, Soft Starting logic allows both machines to ramp up together by calculating a
demand limit for each machine that will be gradually raised over time. The calculated demand limit is raised
by 10% every minute (configurable) until it reaches 100% and Soft Starting is no longer active.
Also, whenever both machines are operating, the upstream machine receives a calculated setpoint that is
higher than the downstream machine, which balances the load between the 2 machines.
If load is insufficient to run both machines, (capacity drops below 35%, or below the default lag chiller enable
load value minus 44% hysteresis), then only the lead machine operates.
When the load conditions increase sufficiently again, as stated above, the lag machine stages on.
Notes for optional functions
Lead Chiller Fault Handing – Assuming single chiller operation, the lag chiller stage should start if the lead
chiller faults
Chiller Rotation – Once you have observed stable operation, set Chiller rotation method to option 6 –
Runtime Equalize. Over time, the run hours of both machines should be roughly equal.
You should also test these functions, if applicable, in the following Properties > Control Program section:
Chiller Shutdowns – verify that the system correctly shuts down when receiving a refrigerant, emergency, or
plant shutdown signal
Demand Limiting – verify that the system demand limit correctly regulates chiller operation when a demand
limit signal is received over the network
Carrier® ChillerVu™
23XRV Series Counterflow Application Guide
8
CARRIER CORPORATION ©2021
All rights reserved

Advertisement

Table of Contents
loading

Table of Contents