Daikin VRV IV Q+ Series Installation And Operation Manual page 23

Hide thumbs Also See for VRV IV Q+ Series:
Table of Contents

Advertisement

WARNING
NEVER remove the spun piping by brazing.
Any gas or oil remaining inside the stop valve may blow off
the spun piping.
6 Wait until all oil has dripped out before continuing with the
connection of the field piping in case the recovery was not
complete.
14.3
Checking the refrigerant piping
14.3.1
About checking the refrigerant piping
Refrigerant piping works are
finished?
No
Yes
The indoor units and/or
outdoor unit were already
No
powered ON?
Yes
Use procedure:
"Method 2: After power ON".
It is very important that all refrigerant piping work is done before the
units (outdoor or indoor) are powered on. When the units are
powered on, the expansion valves will initialise. This means that the
valves will close.
NOTICE
Leak test and vacuum drying of field piping and indoor
units is impossible when field expansion valves are closed.
Method 1: Before power ON
If the system has not yet been powered on, no special action is
required to perform the leak test and the vacuum drying.
Method 2: After power ON
If the system has already been powered on, activate setting [2‑21]
(refer to
"To access mode 1 or
expansion valves to guarantee a refrigerant piping pathway and
make it possible to perform the leak test and the vacuum drying.
DANGER: RISK OF ELECTROCUTION
NOTICE
Make sure that all indoor units connected to the outdoor
unit are powered on.
NOTICE
Wait to apply setting [2‑21] until the outdoor unit has
finished the initialisation.
Leak test and vacuum drying
Checking the refrigerant piping involves:
▪ Checking for any leakages in the refrigerant piping.
RXYQQ8~20U7Y1B
VRV IV Q+ series heat pump
4P546221-1B – 2020.10
Finish piping work.
Use procedure:
"Method 1: Before power ON
(regular method)".
2" [ 4  35]). This setting will open field
▪ Performing vacuum drying to remove all moisture, air or nitrogen
in the refrigerant piping.
If there is a possibility of moisture being present in the refrigerant
piping (for example, water may have entered the piping), first carry
out the vacuum drying procedure below until all moisture has been
removed.
All piping inside the unit has been factory tested for leaks.
Only field installed refrigerant piping needs to be checked.
Therefore, make sure that all the outdoor unit stop valves are firmly
closed before performing leak test or vacuum drying.
NOTICE
Make sure that all (field supplied) field piping valves are
OPEN (not outdoor unit stop valves!) before you start leak
test and vacuuming.
For more information on the state of the valves, refer to
Setup" [ 4  23].
refrigerant piping:
14.3.2
Checking refrigerant piping: General
guidelines
Connect the vacuum pump through a manifold to the service port of
all stop valves to increase efficiency (refer to
Setup" [ 4  23]).
piping:
NOTICE
Use a 2-stage vacuum pump with a non-return valve or a
solenoid valve that can evacuate to a gauge pressure of
–⁠ 1 00.7 kPa (−⁠ 1 .007 bar)(5 Torr absolute).
NOTICE
Make sure the pump oil does not flow oppositely into the
system while the pump is not working.
NOTICE
Do NOT purge the air with refrigerants. Use a vacuum
pump to evacuate the installation.
14.3.3
Checking refrigerant piping: Setup
f
g
A
a
h
i
B
d
C
b
c
e
a
Pressure reducing valve
b
Nitrogen
c
Weighing scales
d
Refrigerant R410A tank (siphon system)
e
Vacuum pump
f
Charge hose
g
Refrigerant charge port
h
Gas line stop valve
i
Liquid line stop valve
j
Outdoor unit
k
To indoor unit
l
Stop valve
m
Field piping
n
Gas flow
o
Stop valve service port
A
Valve A
B
Valve B
C
Valve C
Valve
Valve A
Valve B
Valve C
Liquid line stop valve
14 Piping installation
"Checking
"Checking refrigerant
j
j
j
k
l
o
m
n
State of valve
Close
Open
Open
Close
Installation and operation manual
23

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents