Power-On Procedure - Huawei PDC-0038V4ACIOA Quick Manual

Hide thumbs Also See for PDC-0038V4ACIOA:

Advertisement

Mapping between cable connectors for CAN communications ports.
Connecting cables to the PDU for 1+1 parallel system of UPS2000-G-15 kVA or UPS2000-G-20
kVA (three-phase input three-phase output)
The preceding figure shows how to connect cables when there are two mains inputs. In the case
of one mains input, connect the mains input power cables to the AC BYPASS INPUT ports (the AC
MAINS INPUT ports are not connected).
6

Power-On Procedure

For details, see the
9
6
AC OUTPUT
UPS2000-G-(15 kVA-20 kVA) Quick Guide.
7
4
1
2
AC BYPASS
INPUT
11
8
3
AC MAINS
INPUT
5

Advertisement