Insulation Work - LG MULTI F A2UW16GFA0 Engineering Product Data Book

Hide thumbs Also See for MULTI F A2UW16GFA0:
Table of Contents

Advertisement

2. Guideline for each installation process

2.4 Insulation work

2.4.1 Insulation
1) Operational steps
1
EPDM length should be more
longer than pipe length.
Do not extend EPDM by force.
2) Bending vertical side of insulation
1
Use the original uncut insulation
material.
3) 'L' Fitting connection part insulation
1
All of the fitting connecting parts
should be insulated.
Bring face to face the each end of
EPDM on fitting connection part.
2
Put the pipe in EPDM insulation
carefully so that the pipe will not
get damaged with EPDM.
2
Only in specialcase is the vertical
cutting of the insulation allowed.
2
Make fitting cover to fit the EPDM
insulation fitting cover should be
overlapped with insulation min 1
inch (2.5cm).
3
Bond on both side of cut surfaces
of move sure to use the correct type
of bond for EPDM cut surface
attaching.
3
Bond both sides of the surface of
EPDM and press them together for
long lasting bonding.
3
Bond the both cutting sides of
fitting cover.
Heat pump
4
Dry it until it becomes thick, sticky
and does not get detached.
4
Dry it until it becomes thick and
sticky.
_ 20