Preparations Before Commissioning - Grundfos Fire HSEF FM Europe Series Installation And Operating Instructions Manual

Diesel-powered firefighting system
Table of Contents

Advertisement

Warning
Commissioning must be carried out by authorised
staff.
Warning
The control cabinet of the controller must remain
closed during commissioning.
Do not start the pump until it has been filled with
Caution
water and vented.
The pump must not run against closed valve as this
Caution
may cause an unacceptable temperature increase or
the formation of vapour.
See also installation and operating instructions for
Note
the controller.
You must not change the engine speed setpoint
Caution
(rpm).
Pump set with Clarke diesel engine:
We recommend that you register the diesel engine
before startup. Otherwise, Clarke cannot provide any
Note
warranty if the engine is faulty. Go to
www.clarkefire.com: SERVICE, PARTS &
WARRANTY.

8.2 Preparations before commissioning

The below listed preparation actions are valid for applications
with flooded suction conditions.
1. Check that all screws are tight.
2. Check that all pipes and hoses are installed correctly.
3. Check all electrical connections.
4. Check that all fuses in the control cabinet are switched on.
5. Check the alignment of the coupling. See section
6.4 Alignment.
6. Check that the coupling guard is installed correctly and that all
screws are tightened to 10 Nm for M6 and 25 Nm for M8.
7. Check that all safety devices are installed.
8. Make sure that any storage tank and pump priming tank are
filled with water.
9. Set the pressure switches according to the instructions.
System pressure minus 0.5 bar can be used as a reference
value.
10. Open the isolating valves on the suction and discharge sides.
The static geometric suction pressure from the main water
tank will fill the suction pipe, discharge pipe and pump with
water.
11. Bleed all air from the pump casing and suction pipe by the
opening of the automatic relief valve at the top of the pump.
Rotate the shaft a few times if possible to evacuate any air
trapped inside the impeller passages.
12. Close the isolating valves on the suction and discharge sides.
Fig. 29 Air relief valve
8.2.1 Pump set with diesel engine
Check the level of oil and coolant in the engine prior
Caution
to startup.
See installation and operating instructions for the
Note
diesel engine.
1. Check the V-belt tension.
2. Check the oil level and refill, if necessary.
3. Check the level of coolant and refill, if necessary.
4. Check that all hose connections in the cooling circuit are tight
and leakage-free.
5. Fill the fuel tank with diesel fuel and vent the fuel pipes.
17