How do I relocate the vessel?
1 comments:
Mr. Anderson
March 17, 2025
To relocate the Flamco AirFix P vessel, follow these steps:
1. Shut off the water supply and drain the Airfix P on the water side. Be cautious, as the water may be hot. 2. Remove the cover and valve cap. 3. Release pressure from the Airfix P at the gas top-up valve. 4. Unscrew the Airfix P and carefully remove it, considering its weight if filled with water. 5. Transport and reinstall the vessel at the new location, ensuring compliance with installation guidelines: - Mount Airfix P with the water connection facing downward. - Set the gas pre-charge pressure correctly. - Install a pressure-reducing valve upstream in the pipeline if required. 6. Reconnect and test the system to ensure proper operation.
Dispose of any removed components according to local regulations.
Stainless steel storage vessels & water heaters (12 pages)
Summary of Contents for flamco AirFix P
Page 4
Airfix P vessels can also be used in pressurization systems (glycol max. 50%). Min.- / max. system temperature: Airfix P 2 - 300: - 10 °C / + 100 °C; Airfix P 500 - 5000: - 10 °C / + 70 °C. Installation First use The installation must be carried out by approved personnel only.
Need help?
Do you have a question about the AirFix P and is the answer not in the manual?
Questions and answers
How do I relocate the vessel?
To relocate the Flamco AirFix P vessel, follow these steps:
1. Shut off the water supply and drain the Airfix P on the water side. Be cautious, as the water may be hot.
2. Remove the cover and valve cap.
3. Release pressure from the Airfix P at the gas top-up valve.
4. Unscrew the Airfix P and carefully remove it, considering its weight if filled with water.
5. Transport and reinstall the vessel at the new location, ensuring compliance with installation guidelines:
- Mount Airfix P with the water connection facing downward.
- Set the gas pre-charge pressure correctly.
- Install a pressure-reducing valve upstream in the pipeline if required.
6. Reconnect and test the system to ensure proper operation.
Dispose of any removed components according to local regulations.