ADCP-80-526 • Issue 6 • December 2006
3. Locate the C GND (chassis ground) studs at the rear of the panel as shown in
DETAIL DRAWING
OF GROUNDING
WIRE CONNECTION
4. Connect the ring terminal end of each wire to one of the studs and secure using the nuts
with captive star washers provided (requires 3/8-inch socket). Tighten each stud nut to 23
pound-force inches (2.6 Newton meters) of torque.
5. Route the free end of each chassis grounding wire to an approved office ground source.
6. Cut each chassis grounding wire to length and connect it to the office ground source as
required by local code or practice.
Page 20
© 2006, ADC Telecommunications, Inc.
TIGHTEN STUD NUT TO
23 POUND-FORCE INCHES
(2.6 NEWTON METERS)
OF TORQUE
Figure 15. Chassis Ground Connections
Figure
15.
18868-A