Air Cooled Liquid Coolers Product Manual AHE00050. Both manuals must be carefully examined and instructions should be followed up at all times. Alfa LU-VE does not accept liability for any damage resulting from non-compliance to the instructions as given in the manuals and order-related documents.
The mechanic must perform the repair work according to the standard IEC-60079-19. Under the period of guarantee, always return a faulty motor to the supplier. Do not demolish it. Always use the spare part motor available from Fincoil LU-VE Oy to guarantee its applicability to the operating conditions.
Page 34
(vertical air flow) to the correct position at installation. ™ Two turning supports with locking bolts are included in the delivery of the AlfaSolar S/SR units. Note: Remove the locking bolts before installing the turning supports to the unit.
Install the external tubes so that their weight, vibration or heat expansion does not strain the tubes of the heat transfer section. You can use flexible couplings to ensure this. Contact Alfa LU-VE for information on the flexible expansion joint solution.
Page 57
Availability 4 m legs are delivered loose. ™ Figure 33: Installation of 1m leg extension to AlfaSolar S/SR 1. Slide the extensions over the standard legs. 2. Install the vertical leg supports with M10 grade 8.8 bolts. The required M10 bolts, nuts and spring washers are included in the delivery.
Figure 34: High mounting leg installation (AlfaSolar SR series) 7.9.5 Vibration dampers The suitability of the elastic vibration dampers supplied by Fincoil LU-VE Oy has been ensured. Proceed as follows: 1. Check the load weight and ensure that the correct dampers for this load are available.
Page 71
The necessary intervals between servicing depend upon the specific application. The operator stipulates the service interval according to the operating conditions. Alfa LU-VE gives the following guidelines for regular service inspection intervals and tasks: Task Inspection Interval Check the cleanness and visual condition of the heat transfer section;...
Fasten all the connection terminals correctly. 1 year You can use the liquid cooler top cover plates as a service desk. Alfa LU-VE recommends installing handrails and using safety harness. Solutions for handrails and mounting legs are available from Alfa LU-VE.
Note the slippery edges. You can use the liquid cooler top cover plates as a service desk. Alfa LU-VE recommends installing handrails and using safety harness. Solutions for handrails and mounting legs are available from Alfa LU-VE.
If the fan makes unusual noise, stop it immediately and check the fixing of the fan and fan motor. When necessary, replace the motor by a new spare part motor available from Fincoil LU-VE Oy. Caution: Operate the IEC-fans for 3…4 hours during stand-stills.
Need help?
Do you have a question about the AlfaSolar S and is the answer not in the manual?
Questions and answers