Commissioning Via Abb Installer For Solar Inverters Mobile App - ABB PVS-175-TL Quick Installation Manual

Solar inverter a.1 version
Hide thumbs Also See for PVS-175-TL:
Table of Contents

Advertisement

Quick Installation Guide - PVS-175-TL "A.1 Version"
38

13.1 Commissioning via ABB Installer for Solar Inverters mobile APP

ABB Installer for Solar Inverters APP is available for Android mobile devices with an Android version of 6.0.1
or greater (for iOS mobile devices will be implemented soon) and could be downloaded and installed from
Play Store.
The requirements to complete the procedures are listed below:
• ABB Installer for Solar Inverters APP installed on mobile device.
• Enabled installer account for ABB Installer for Solar Inverters APP (The account could be created in the
mobile app directly following the dedicated wizard procedure).
• Manual claiming of the inverters to be commissioned.
SN WLAN: SSSSSSSSSS
PN WLAN:
VKA
.V2P
53.1
Mac Address:
AA:BB:CC:DD:EE:FF
Remove and apply on the plant documentation
SN WLAN: SSSSSSSSSS
SN Wiring Box: ZZZZZZZZZZ
MAC: AA:BB:CC:DD:EE:FF
PK: 0000 - 0000 - 0000- 0000
Follow the procedure below to commission the inverter:
D
NOTE –
This inverter can be powered both with AC or DC sources. In case of DC source is used, make
sure that irradiation is stable and adequate for the inverter commissioning procedure to be completed.
• Close the DC disconnect switches (19) to supply the inverter with input voltage from the photovoltaic
generator or close the AC switch downstream of the inverter (and AC disconnect switch (09) for the -S2,
-SX2 wiring box version) to supply the inverter with AC grid voltage. In the pre-commissioning phase the
"Alarm" LED keeps quickly flashing, "Power" and "GFI" LEDs are OFF.
• Perform the installation wizard steps with ABB Installer for Solar Inverters APP enabling the transferring
the settings to all the claimed inverters.
• After the commissioning via ABB Installer for Solar Inverters APP is completed, the inverter changes the
behavior of the "Power" and "Alarm" LEDs (08), in relation of the input voltage value:
Input voltage
LED Status
Power = Flashing
Vin < Vstart
Alarm = OFF
Power = Flashing
Vin > Vstart
Alarm = ON
• Depending of the supply source used to complete the installation wizard steps, close the disconnect switch
of missing voltage sources: In case of missing AC source close the AC switch downstream of the inverter
(and AC disconnect switch (09) for the -S2, -SX2 wiring box version); In case of missing DC source close the
DC disconnect switches (19).
• When the input voltage is sufficient to allow the connection to the grid, the inverter will check the grid
voltage, measure the isolation resistance of the photovoltaic field with respect to ground and performs
other auto-diagnostic checks. During the preliminary checks on the parallel connection with the grid, the
"Power" LED keeps flashing, the "Alarm" and "GFI" LEDs are OFF. The inverter will ONLY connect to the grid
if all parameters fall within the ranges foreseen by current regulations.
• If the outcome of the preliminary checks to grid synchronization are positive, the inverter connects and
starts to export power to the grid. The "Power" LED remains fixed on while the "Alarm" and "GFI" LEDs are
OFF.
D
NOTE –
For more details about commissioning and any other functionalities of the Installer for Solar
Inverters mobile APP please contact ABB customer support.
The claiming process consists of indicating which inverters are to be
commissioned.
• Claiming process can be performed by:
• taking pictures of the QR codes (J) of single inverter units (printed on
H
the Communication identification label) (recommended).
• manual insertion of the MAC address (H) and related product keys
J
(I) (printed on the Communication identification label) of all the
inverters that shall be commissioned.
I
• scanning and selecting of SSIDs associated to the Wi-Fi networks
generated by each inverter to commission.
Description
The input voltage is not sufficient to enable connection to the grid.
The input voltage is sufficient to enable connection to the grid:
the inverter waits for the grid voltage to be present to make the
connection to the grid.