SOLIS -EPM3-5G-Plus Quick Installation Instructions

SOLIS -EPM3-5G-Plus Quick Installation Instructions

Export power manager

Advertisement

Quick Links

Quick installation
instructions
Export Power Manager
Solis-EPM3-5G-Plus
Ningbo Ginlong Technologies Co., Ltd.
C
1
Determine location of EPM
Following minimum clearance is required.
300mm
Install the EPM
2
Step 1: Mark A,B,C,D mounting holes on the wall.
A
C
Step 2: Drill four φ8 holes and fix the bracket onto the wall
with expansion bolts.
Expansion screws
Bracket
Step 3: Hang the EPM on the bracket by the steps below.
300mm
Step 4: Fix the two locking screw on both side of the bracket
and connect the grounding wire to the grounding screw.
M4 locking screw
B
3
Connect cables
D
1. Grid input cable -> Grid Port
Connect the grid input cables to the grid connector and
then to the Grid port of the EPM as described below.
3 connect
to L3
connect to N
M4 locking screw
Groundingscrew
2 connect
to L2
1 connect
to L1
connect to

Advertisement

loading
Need help?

Need help?

Do you have a question about the Solis-EPM3-5G-Plus and is the answer not in the manual?

Questions and answers

Summary of Contents for SOLIS Solis-EPM3-5G-Plus

  • Page 1 Quick installation 300mm 300mm instructions Export Power Manager Step 4: Fix the two locking screw on both side of the bracket Solis-EPM3-5G-Plus and connect the grounding wire to the grounding screw. M4 locking screw Install the EPM M4 locking screw Groundingscrew Step 1: Mark A,B,C,D mounting holes on the wall.
  • Page 2: System Diagram

    1A or 5A. Stripped length=3mm The following table describes the optional CT package that can be ordered separately from Solis. (Please evaluate your system requirements before placing the order) 2. RS485 cable -> COMM-INV Port Connect the 2-pin connector to the COMM-INV Port of the...