Checklist for use of EP-19xx Modules
Equipment type / equipment ID
Version: HW/FW
Reviewer 1:
Notes:
No.
Requirement (mandatory)
1
During commissioning, the intentional starting up of potentially
hazardous processes is only possible while looking into the
danger zone at the same time.
2
Commissioning is carried out according to the guidelines from
the planning stage and/or the manual.
3
All inputs were configured.
Requirement (optional)
4
The safety clearances to be maintained are measured according
to the implemented reaction and delay times.
Date / Signature of Reviewer 1:
GFK-2956A
Appendix A. Checklist for Use of EP-19xx Modules
Sheet 3/3: Commissioning and configuration
Date:
Reviewer 2:
Yes
Yes/No
Date / Signature of Reviewer 2:
November 2017
Remark
Remark