Commissioning; Check Before Power-On - Huawei SUN2000 Series User Manual

Hide thumbs Also See for SUN2000 Series:
Table of Contents

Advertisement

SUN2000-(3KTL-10KTL)-M0
User Manual

6.1 Check Before Power-On

Table 6-1 Installation checklist
No.
1
2
3
4
5
6
7
8
9
Issue 04 (2019-10-18)
Check Item
SUN2000 installation
Smart Dongle
Cable layout
Cable tie
Grounding
Turn off the switches
Cable connections
Unused terminals and ports
Installation environment
Copyright © Huawei Technologies Co., Ltd.
6

Commissioning

Acceptance Criteria
The SUN2000 is installed correctly,
securely, and reliably.
The Smart Dongle is installed correctly and
securely.
Cables are routed properly as required by the
customer.
Cable ties are secured evenly and no burr
exists.
The ground cable is connected correctly,
securely, and reliably.
The DC SWITCH and all the switches
connected to the SUN2000 are set to OFF.
The AC output power cable and DC input
power cable are connected correctly,
securely, and reliably.
Unused terminals and ports are locked by
watertight caps.
The installation space is proper, and the
installation environment is clean and tidy,
without foreign matter.
6 Commissioning
53