7 Commissioning

7
Commissioning
NOTICE
General
commissioning
commissioning instructions in this chapter, a general
commissioning checklist is also available on the Daikin
Business Portal (authentication required).
The general commissioning checklist is complementary to
the instructions in this chapter and can be used as a
guideline and reporting template during the commissioning
and hand-over to the user.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.
NOTICE
Make sure both air purge valves (one on the magnetic filter
and one on the backup heater) are open.
All automatic air purge valves must remain open after
commissioning.
INFORMATION
The software is equipped with an "installer-on-site" mode
([9.G]: Disable
protections), that disables automatic
operation by the unit. At first installation, setting Disable
protections is by default set to Yes, meaning automatic
operation is disabled. All protective functions are then
disabled. To enable automatic operation and the protective
functions, set Disable protections to No.
12 hours after the first power-on, the unit will automatically
set Disable protections to No, ending "installer-on-site"
mode and enabling the protective functions. If –  after first
installation  – the installer returns to the site, the installer
has to set manually Disable protections to Yes.
7.1

Checklist before commissioning

After the installation of the unit, first check the items listed below.
Once all checks are fulfilled, the unit must be closed. Power-up the
unit after it is closed.
You read the complete installation instructions, as
described in the installer reference guide.
The indoor unit is properly mounted.
The outdoor unit is properly mounted.
The following field wiring has been carried out according
to this document and the applicable legislation:
▪ Between the local supply panel and the outdoor unit
▪ Between indoor unit and outdoor unit
▪ Between the local supply panel and the indoor unit
▪ Between the indoor unit and the valves (if applicable)
▪ Between the indoor unit and the room thermostat (if
applicable)
The system is properly earthed and the earth terminals
are tightened.
Installation manual
26
checklist.
Next
to
the
The fuses or locally installed protection devices are
installed according to this document, and have NOT been
bypassed.
The power supply voltage matches the voltage on the
identification label of the unit.
There are NO loose connections or damaged electrical
components in the switch box.
There are NO damaged components or squeezed
pipes on the inside of the indoor and outdoor units.
Backup heater circuit breaker F1B (field supply) is
turned ON.
The correct pipe size is installed and the pipes are
properly insulated.
There is NO water leak inside the indoor unit.
The shut-off valves are properly installed and fully open.
The automatic air purge valves are open.
The pressure relief valve purges water when opened.
The domestic hot water tank is filled completely.
7.2

Checklist during commissioning

The minimum flow rate during backup heater/defrost
operation is guaranteed in all conditions. See "To check
the water volume and flow rate" in
piping" [ 4  7].

To perform an air purge.

To perform a test run.
To perform an actuator test run.
Underfloor screed dryout function
The underfloor screed dryout function is started (if
necessary).
7.2.1

To check the minimum flow rate

1 Check with the hydraulic configuration which space
heating loops can be closed by mechanical,
electronic, or other valves.
2 Close all space heating loops that can be closed
(see previous step).
3 Start the pump test run (see
run" [ 4  27]).
actuator test
(a)
4 Read out the flow rate
and modify the bypass valve
setting to reach the minimum required flow rate + 2 l/
min.
(a)
During pump test run, the unit can operate below the
minimum required flow rate.
Minimum required flow rate
25 l/min
7.2.2
To perform an air purge
Conditions: Make sure all operation is disabled. Go to [C]:
Operation and turn off Room, Space heating/cooling and Tank
operation.
"4.1  Preparing water
"7.2.4 To perform an
ETVH/X16S18+23DA6V+9W(G)
Daikin Altherma 3 H HT F
4P586454-1 – 2019.07

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents