8. Switch the generator's main circuit breaker OFF and put the
mode switch in the OFF position to shut down the generator.
9. With utility power still OFF, use the transfer handle to move the
main contacts to the UP (utility) position.
10. Close the main breaker to turn utility power ON.
11. Switch the generator's main breaker to the ON position and
put the mode switch in AUTO.
12. Shut OFF utility power and make sure the generator starts
automatically after the line interrupt delay.
13. Switch the utility breaker to ON and make sure that power is
automatically transferred back to the utility.
14. Shut OFF utility power again to automatically start the
generator. When power has transferred to the generator, close
each of the breakers in the distribution panel one at a time
until the generator has accepted the entire load.