cashco FL-200 Maintenance & Assembly Instructions

Inline thermal check valve

Advertisement

INSTRUCTION NO. IOM-FL200
REFERENCE DATA:
Fl-200 Series Assembly Drawing No. A88-60200-00.

INSTALLATION:

1. Clean the piping of all foreign material including chips, welding scale, oil, grease and dirt before installing the thermal
trip valve.
2. In placing thread sealant on pipe ends prior to engagement, ensure that excess material is removed and not allowed
to enter the thermal trip valve upon startup.
3. Flow Direction: Install so the flow direction matches the flow arrow on the body of the thermal trip valve.

PRINCIPLE OF OPERATION:

1. When the valve is installed it is open.
2. This valve will stay open until it is actuated by the fusible link.
3. This will cause the valve to close.

MAINTENANCE:

1. All valves are leak tested at the factory at 200 PSIG and should be externally leak tight after installation. If after pro-
longed ser vice the valve should leak externally, it is recommended that the valve be replaced or sent to the factory
for rebuilding.
MAINTENANCE & ASSEMBLY INSTRUCTIONS
Model FL-200
Inline Thermal Check Valve
IOM-FL 200
12-04

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the FL-200 and is the answer not in the manual?

Questions and answers

Summary of Contents for cashco FL-200

  • Page 1 Model FL-200 Inline Thermal Check Valve INSTRUCTION NO. IOM-FL200 REFERENCE DATA: FL-200 Series Assembly Drawing No. A88-60200-00. INSTALLATION: 1. Clean the piping of all foreign material including chips, welding scale, oil, grease and dirt before installing the thermal trip valve.
  • Page 2 THERMAL CHECK VALVE FL-200 SERIES Fusible Link NOTES: 1. Maximum pressure rating 130 psig (896 kPa) WOG. 2. No changes shall be made to parts, material or manufacturing process without prior ap prov al by Factory Mutual Research Corporation. 3. All valves to be assembled, inspected and test ed in strict accordance with Cashco Standard S-1549.

Table of Contents