INSTALLATION INSTRUCTIONS
E. Install Copper Lineset
• The standard line set length is 25 feet. If
the installation length is different, adjust the
refrigerant charge by 0.2 oz/ft if the liquid line
is 1/4", or 0.5 oz/ft if the liquid line is 3/8".
• See table on page 15.
• Cut the line set to length.
• Place nut over the pipe and then flare with the
R-410A flaring tool.
NOTE: Follow standard practices for creating
pipe flares. When cutting and reaming the
tubing, use caution to prevent dirt or debris
from entering the tubing. Remember to place
nut over the tubing before flaring.
• To join the line set, directly align the tubing
flare to the fitting on the other pipe. Slide the
nut onto the fitting and hand tighten.
• Torque the fittings according to the
specifications shown in the torque chart below.
Forced fastening without careful centering may
union
Flare nut
damage the threads and cause a refrigerant leak.
Pipe Diameter(ǿ)
Liquid side6.35mm(1/4")
Liquid/Gas side9.52mm(3/8") 42 N.m/30.1Ft.lbs
Gas side 12.7mm(1/2")
er
Torque wrench
Gas side 15.88mm(5/8")
• Two wrenches are required to
join the flare connection; one
standard wrench and one torque
wrench adjusted to the proper
settings.
• Repeat the process for
attaching the other end of the
line set.
CAUTION
B
Outdoor unit
Outdoor unit
B
A
16
Step 3 - Installation of the Outdoor Unit (Cont.)
Fastening torque
18N.m/13.3Ft.lbs
55N.m/40.6Ft.lbs
60 N.m/44.3Ft.lbs
Half union
Spanner
Outdoor unit
Indoor unit
B
A
A
Max. Elevation: A Max
= 33ft / 10m (09k / 12k)
= 50ft / 15m (18k / 24k)
In case the height of A is more than
15ft / 5m, an oil trap should be
Oil trap
installed every 16-23ft /5-7m
Indoor unit
Max. Length: B Max
= 50ft / 15m (09k / 12k)
= 83ft / 25m (18k / 24k)
F. Leak Test
FlexFit multi-zone models 2U18MS and 3U24MS do
not have master service valves. Perform the following
steps for EACH line set.
The FlexFit multi-zone model 4U36MS and Arctic multi
models 2U20EH and 3U24EH have a master service
valve. Performing the following steps will test ALL line
sets.
• Remove the cap on the service valve.
• Using a tank of dry nitrogen and approved regulator,
charge the system with 150 psig of dry nitrogen
using mini-split adapter to connect the valve.
• Check for leaks at the flare fittings using soap
bubbles or another detection device. If a leak is
detected, make repairs to the fittings and recheck.
If no leaks are detected within 3 minutes, proceed.
• Using the same tank/regulator, charge the system
to 300 psig.
• Check for leaks as earlier. If no leaks are detected
within 3 minutes, proceed.
• Using the same tank/regulator, charge the system
to 500 psig.
• Check for leaks as earlier. Keep system pressurized
for at least 20 minutes.
WARNING
containing them for pressure testing. Do not use
mixtures of hydrogen containing refrigerant and air
above atmospheric pressure for pressure testing as
they may become flammable and could result in an
explosion. Refrigerant, when used as a trace gas,
should only be mixed with dry nitrogen for pressurizing
units. Failure to follow these recommendations could
result in death or serious injury as well as equipment or
Forced fastening without careful centering may
property damage.
Flare nut
damage the threads and cause a refrigerant leak.
Pipe Diameter(ǿ)
Liquid side6.35mm(1/4")
G. System Evacuation
Liquid/Gas side9.52mm(3/8") 42 N.m/30.1Ft.lbs
NOTE– Do not open service valve.
Gas side 12.7mm(1/2")
Torque wrench
• Remove the suction line cap and attach a manifold
Gas side 15.88mm(5/8")
gauge, micron gauge, and vacuum pump to
the suction line port using adapter AD-87 (see
illustration).
• Evacuate the system to at least 350 microns.
• Close the vacuum pump valve and check the micron
gauge. If the gauge rises above 150 microns in 60
seconds, the evacuation is incomplete or there
is a leak in the system. If the gauge does not rise
Indoor unit
above 150 microns in 60 seconds, the evacuation is
complete.
• Once evacuation is complete, remove the adapter
and hose connection from the suction line port and
replaced the cap.
Do not use acetylene, oxygen or
compressed air or mixtures
Fastening torque
18N.m/13.3Ft.lbs
55N.m/40.6Ft.lbs
60 N.m/44.3Ft.lbs
31-5000001 Rev. 1