Installation Instructions
Steps for Changing Cabinet Orientation to Vertical Downfl ow OR Horizontal
Left Orientation
1.
Remove the screws and front panel and disconnect the T2 sensor wire's
molex plug from the board (Figure 10, Step 1).
2.
Pull out the coil with the sensor wire attached (do not disconnect the T2
sensor from the liquid pipe on the A coil). Pull the sensor wire through the
liquid line hole in the cabinet cover (see 2A on Figure 10, Step 2).
STEP 1
Figure 11
Vertical Downfl ow & Horizontal Left Applications Conversion
Bosch Thermotechnology Corp. | 02.2019
3.
STEP 3
3A
Replace the coil in the correct orientation and secure in place. Remove the
knockout (labeled 3A in Figure 10, Step 3) in the side of the cabinet, and
add the rubber grommet from the included accessory bag. Connect the
molex plug end of the sensor wire to the control board (insert wire through
the knockout in the cabinet). (Figure 10, Step 3).
STEP 2
2A
Bosch IDS BVA 2.0 | 11