1
Installation and Startup Guide
This document covers the installation of cMT3071/3072 Series HMI, for the detailed
specifications and operation, please refer to Datasheet, Brochure and EasyBuilder Pro User
Manual. Please read all warnings, precautions, and instructions on the device carefully before
use.
Install Environment:
NEMA Rating
The
HMI product is NEMA 4 rated (Indoor Only).
The
HMI product has been tested to conform to European CE requirements. This
Electrical
means that the circuitry is designed to resist the effects of electrical noise. This
Environment
does not guarantee noise immunity in severe cases. Proper wire routing and
grounding will insure proper operation.
(1) Make sure that the displays are installed correctly and that the operating
limits are followed. Avoid installing units in environments where severe
mechanical vibration or shocks are present.
(2) Do not operate the unit in areas subject to explosion hazards due to
flammable gases, vapors or dusts.
Environmental
(3) Do not install the unit where acid gas, such as SO2 exists.
Considerations
(4) This device should be mounted in the vertical position and for use on the flat
surface enclosure.
(5) Conform to UL 61010-2-201 safety requirement for use in Pollution Degree
2 Environment.
(6) Relative Humidity: 10% ~ 90% (non-condensing)
Cleaning
Disconnect this device from AC outlet before cleaning. Clean the device using
Considerations
cloths wetted with clean water. Do not use liquid or spray detergents for cleaning.
Unpacking the Unit
2
Unpack and check the delivery. If damage is found, please contact the supplier.
NOTE:
Place the operator panel on a stable surface during installation. Dropping it or letting it
fall may cause damage.
The package includes:
(1) Installation Instruction, 2-sided A4 *1 (2) Human Machine Interface *1 (3) Power Connector *1
(4) Brackets & Screws *1 pack (5) Fuse 3.15A/250V 5*20mm *1 (6) USB Stick Clamp & Tying Strap *1
USB Stick Clamp Usage
Combining the USB Stick with the clamp and the tying strap can prevent USB stick from disconnecting
with HMI when strong vibration is present.
1. Insert the USB connector to the clamp and tie them together with the tying strap.
2. Press the spring and insert the USB stick into HMI.
Installation Instruction
3
Installation Instructions
Use a control box that provides enough stiffness.
Cutout Dimension: 192 mm x 138 mm. Secure the
operator panel in position, using all the fastening
holes and the provided brackets and screws. Screw
Torque: 2.6 ~ 3.9 lbf.in. (For reaching waterproof
effect and preventing the panel from being deformed.)
Plan for adequate space around the unit and inside
the enclosure, for ventilation and cables. Consider the
heat from other devices inside the enclosure. The
ambient temperature around the unit must be 0 ~
50°C
Minimum required clearances (along the overlay): Top / Bottom / Sides 15 mm
Maximum panel thickness: 4.5 mm
The aluminum flat-sheet at the back of the unit is a heat sink. Please be careful not to touch the heat
sink since its heat can rise to 70°C in maximum when the unit is running. Planning for a 3cm space
between the back of the unit and other devices is recommended.
4
Power Connections
Power Connector Specifications:
Wire AWG: 28~12
Operating Temperature: -40°C ~105°C
Screw Torque: 3.47 lbf-in (max.)
NOTE:
1. Connect positive DC line to the '+' terminal and the
DC ground to the '-' terminal.
2. When downloading project using a USB cable, do
not connect HMI with PLC and PC simultaneously, for
electric potential difference may result in damage to
HMI or PC.
System Settings
5
When HMI is powered up and displays image, press
the round Start Button in the upper-left corner of the
screen to open the Setting dialog box. Tap the lock
icon
and log in. (Default System Password:
111111)
Go to the Network tab, and setup your network.
In Setting dialog box you can see device information,
configure general settings, set HMI
Time/Date/Name, and more.
6
EasyBuilder Pro Software Settings
Launch EasyBuilder Pro software, select your project file, press F7 shortcut key to open the download
dialog box: Select Ethernet > IP tab > Enter your HMI IP > Click Download to download this project
file to HMI.
Using screensaver and backlight saver is recommended in order to avoid image persistence caused
by displaying the same image on HMI for a long time.
(Please refer to EasyBuilder Pro User Manual for software operation details.)

Advertisement

loading

Summary of Contents for Maple Systems cMT3071 series

  • Page 1 cMT3071/3072 series Installation Instructions Use a control box that provides enough stiffness. Cutout Dimension: 192 mm x 138 mm. Secure the Installation Instruction operator panel in position, using all the fastening holes and the provided brackets and screws. Screw Torque: 2.6 ~ 3.9 lbf.in. (For reaching waterproof effect and preventing the panel from being deformed.) Plan for adequate space around the unit and inside Installation and Startup Guide...
  • Page 2: Battery Replacement

    NOTE: Make sure that all local and national electrical standards are met when CAUTION Communication Connections installing the unit. Contact your local authorities to determine which codes apply. Use power output that meets SELV (Safety Extra-Low Voltage) requirements. The unit can be NOTE: powered by DC power only, voltage range: 10.5~28VDC, compatible with most controller DC COM2 and COM3 [RS485] 2W support MPI 187.5K, please use one at a time.

This manual is also suitable for:

Cmt3072 series