1. Installation (Connecting the piping between indoor and outdoor unit)
Indoor unit
Gas cylinder
R22
Purge the air
• Installation
(1) Connect the piping between the indoor and out-
door unit firmly.
– Incorrect connection may cause the leakage and
incomplete vacuuming.
(2) Attach the charging hose (manifold gauge) to the
service port.
– Charging hose is necessary to check the pressure
and to inject R22 for leakage test.
– The valve of charging hose must be closed before
being connected.
(3) Inject the 100~300g R22 through the charging hose
opening the valve.
(4) Check the joint part using a gas detector or soapy
water for leakage.
– On checking, the service valve of main service port
must be closed, this test is only for checking whether
pipe connection is ok or not.
Liquid side
Gas side
Lo
–31–
(5) If there is no leakage, discharge R22 in piping com-
pletely into tank for retrieving.
– Complete discharge is needed for vacuuming.
– If leakage is found, please fasten the joint more tight-
ly.
(6) After closing the valve of charging hose, discon-
nect the tank and connect the vacuum pump to
charging hose and open the valve again for vacu-
uming.
(7) Turn on the vacuum pump until the pressure drops
below 0kg/cm
2
.
(8) After vacuuming, disconnect the vacuum pump and
open the spindle of service port (liquid-side) slight-
ly for 30 sec and then open the spindle of (gas side)
with hexagonal wrench.
(9) Open the liquid side completely first and then the
gas side fully in order.
Outdoor unit