GENERAL INFORMATION GENERAL SAFETY INFORMATION PRECAUTIONS The operation of any appliance that uses electrical power de- Check that the product is complete, undamaged and as mands that a number of fundamental safety precautions be ordered as soon as you receive it. Report any discrepan- respected.
DESCRIPTION OF THE APPLIANCE IDENTIFICATION double-coil solar boilers, with solar heaters can be iden- TBPS KOMPACT TBPS KOMPACT pre-fitted solar station, are available in three different mod- tified by: els, can be integrated in solar systems for the production of...
GENERAL INFORMATION SYSTEM LAYOUT STORAGE CYLINDER SOLAR STATION Storage cylinder Return Valve (solar plant return) with built-in non-return Top coil valve Preset for lifting handles (accessory) and/or device Delivery Valve (solar plant delivery) with built-in non-re- grounding point turn valve Bottom coil Outlet temperature gauge Flange for heater inspection...
GENERAL INFORMATION TECHNICAL SPECIFICATIONS TBPS KOMPACT DESCRIPTION Type of storage cylinder Verticale,Vetrificato Heat exchanger layout Verticale a sezione ellittica Storage cylinder capacity Useful non-solar volume (Vbu)* Solar usable volume (Vsol)** Diameter of storage cylinder with insulation Diameter of storage cylinder without insulation...
GENERAL INFORMATION TBPS KOMPACT EMPTYING IN 10’ PERFORMANCE RELATING TO INTEGRATION COIL Quantity of domestic water obtained in 10’ with heater pre-heated to 60°C (*) and primary exchanger at the indicated delivery temperature, considering an increase of the domestic water temperature of 30°C between inlet and outlet (ac- cording to EN 12897).
UNPACKING THE PRODUCT PLACE OF INSTALLATION solar heaters are supplied in a storage cylinders can be in- TBPS KOMPACT TBPS KOMPACT single package on a wooden pallet. stalled in any room where there is no specific requirement for The boiler comes with a solar station supplied with solar reg- an electrical protection rating higher than IP X0D.
INSTALLATION WATER CONNECTIONS 100mm TBPS KOMPACT DESCRIPTION Expansion tank fitting 1/2” M Ø Domestic hot water outlet 1” M Ø Outlet from boiler 1” M Ø Return to boiler 1” M Ø Outlet from solar collector 1” M Ø Return to solar collector 1”...
INSTALLATION TYPICAL WATER SYSTEM SCHEMATICS ELECTRICAL CONNECTIONS The diagram below shows the solar regulator default setting. The following is mandatory: - have an omnipolar magneto-thermal circuit breaker and a disconnecting switch compliant with the prevail- IMP 1 ing standards of the installation country - respect the polarity of the L1 (Phase) - N (Neutral) con- nections - use cables with insulation and cross section conform-...
Page 11
INSTALLATION Sensor connections - Route probe cables through the cable guides (F), the fairleads (Ps), the passages on the insulation (Is), the solar station outlets (Us/Ua) and connect them to termi- nal board M4 of solar regulator (terminals S1-S2-S3-S4) making reference to the instructions provided in the specific regulator manual.
INSTALLATION SYSTEM FLUSHING Before filling the system with mixture of water and glycol, it is necessary to flush the pipes of the solar system to eliminate all residues of fluid or scale. Proceed as follows. - Turn handle on valve (VR) clockwise - Open taps (A) and (B) on the return tube - Flush water in through the cock (B) and wait for it to come out of the cock (A)
INSTALLATION SYSTEM FILLING COCK To fill the system, proceed as follows: - Connect the filling pump (PC) as shown - Turn handle on valve (VR) clockwise Before filling the system: Open taps (A) and (B) on the return tube - Cut power off to the solar station and to the connected - Open manual degassing tap and any bleeder valve, integration system, by setting the system's main switch located at the highest points of the system, and keep...
COMMISSIONING AND MAINTENANCE INTERVENTIONS ON THE HYDRAULIC SYSTEM Draining the system - Connect a rubber hose to taps (A) and (B) - Connect the opposite end to a vessel - Open system drain taps and allow full drainage - Close system drain taps and remove the rubber hose - The exhausted heat transfer fluid must be disposed of according to the prevailing regulations, pursuant to the instructions provided in the safety data sheet supplied...
END USER END USER INSTRUCTIONS Refer to the GENERAL SAFETY INFORMATION and PRECAUTIONS section for safety-related information. START-UP TEMPORARY SHUTDOWN The heater commissioning must be performed by Technical To reduce to the environmental impact and save energy, in Assistance Centre personnel. case of brief absences, week-ends, short trips, etc., and with Under certain circumstances, such as after long periods of external temperatures above 0°C, set the heater temperature...
Page 16
Via Mussa, 20 Z.I. 35017 - Piombino Dese (PD) www.thermital.it The manufacturer strives to continuously improve all products. Appearance, dimensions, technical specifications, standard equipment and accessories are therefore liable to modification without notice.
Need help?
Do you have a question about the TBPS KOMPACT and is the answer not in the manual?
Questions and answers