Cabling Procedure - Liebert NX 10kVA Installation Manual

Nx series 208v, 60hz
Table of Contents

Advertisement

2.1.7

Cabling Procedure

CAUTION
!
The operations described in this section must be performed by authorized electricians or
qualified technical personnel. If you have any difficulties, contact your local Liebert
representative or Liebert Global Services.
NOTE
Hydraulic pressure pliers, combinative tools and piston ring pliers should be used to connect
AC wiring.
Once the equipment has been positioned and secured for operation, and the battery and ground col-
lars have been connected (see 2.1.4 - Cable Connections), connect the power cables as described
below. (Study the reference drawing in 7.0 - Installation Drawings.)
1. Verify that all incoming high and low voltage power circuits are de-energized and locked out or
tagged out before installing cables or making any electrical connections.
2. Remove the left side panel to gain access to the connections bars.
3. Connect the safety ground and any necessary bonding ground cables to the copper ground busbar
located on the bottom of the equipment below the power connections. All cabinets in the UPS
must be connected to the user's ground connection.
NOTE
The grounding and neutral bonding arrangement must comply with the National Electrical
Code and all applicable local codes.
4. Identify and make power connections with incoming cables according to Steps 5 through 11.
Common Input Connections
5. For common bypass and rectifier inputs, connect the AC input supply cables between the power
distribution panel and the UPS input busbars (A-B-C terminals) and tighten the connections to
44 lb-in. (5 N-m) (M6 bolt).
6. The input neutral cable must be connected to the input neutral busbar (N). See Figure 5.
Dual Input Connections
7. For bypass connect the AC input supply cables between the power distribution panel and the UPS
input busbars (A-B-C terminals) and tighten the connections to 44 lb-in. (5 N-m) (M6 bolt).
8. For Rectifier Input connect AC input supply cables between the power distribution panel and the
UPS input circuit breaker (A-B-C terminals)
9. The bypass input neutral cable must be connected to the input neutral busbar (N). See Figure 5.
Output System Connections—Ensure Correct Phase Rotation
10. Connect the system output cables between the UPS output busbars (A-B-C N terminals) and the
critical load and tighten the connections to 44 lb-in. (5 N-m) (M6 bolt).
WARNING
!
If the load equipment will not be ready to accept power on the arrival of the commissioning
engineer, then ensure that the system output cables are safely isolated.
Internal UPS Battery Connections
The UPS internal batteries will be connected at the factory, EXCEPT the Anderson connections
between the shelves and to the fuses.
WARNING
!
The DC bus is live when this internal battery connection is made. This connection is to be
performed ONLY by Liebert Global Services at startup.
Observe the battery cable polarity. Be sure that the battery connector is made with the cor-
rect polarity.
11. Refit all protective covers removed for cable installation
13
Electrical Connections

Advertisement

Table of Contents
loading

This manual is also suitable for:

Nx 15kvaNx 20kvaNx 30kva

Table of Contents