*In situations that have multiple units, a 48" minimum clearance is
required between the condenser coils.
Adequate clearance around the unit should be kept for safety, ser-
vice, maintenance, and proper unit operation. A total clearance
of 75" on the main control panel side of the unit is recommended
to facilitate possible fan shaft, coil, and electric heat. A clearance
of 48" is recommended on all other sides of the unit to facilitate
possible compressor removal, to allow service access and to in-
sure proper ventilation and condenser airflow. The unit must not
be installed beneath any obstruction. The unit should be installed
remote from all building exhausts to inhibit ingestion of exhaust
air into the unit fresh air intake.
ROOF CURB INSTALLATION

ROOF CURB POST-INSTALLATION CHECKS

After installation, check the top of the curb, duct connection frame
and duct flanges to make sure gasket has been applied properly.
Gasket should be firmly applied to the top of the curb perimeter,
duct flanges and any exposed duct connection frame. If gasket is
loose, re-apply using strong weather resistant adhesive.
P
ROTRUSION
Inspect curb to ensure that none of the utility services (electric)
routed through the curb protrude above the curb.
I
,
F PROTRUSIONS EXIST
DO NO ATTEMPT TO SET UNIT ON CURB
INSULATED
PANELS
CAUTION

ROOF TOP DUCT CONNECTIONS

Install all duct connections on the unit before placing the unit on
rooftop.
H
D
ORIZONTAL
ISCHARGE
Refer to IOD-7006 included in the literature pack for installing hori-
zontal duct covers.
Flexible duct connectors between the unit and ducts are recom-
mended. Insulate and weatherproof all external ductwork and
joints as required and in accordance with local codes.
12"
6 3/16"
HORIZONTAL DISCHARGE DUCT CONNECTIONS
T
O PREVENT PROPERTY DAMAGE, THE UNIT SHOULD REMAIN IN AN UPRIGHT
POSITION DURING ALL RIGGING AND MOVING OPERATIONS.
LIFTING AND MOVING WHEN A CRANE IS USED, PLACE THE UNIT IN AN
ADEQUATE CABLE SLING.
I
F UNITS ARE LIFTED TWO AT A TIME
CONDENSER END OF THE UNIT MUST NOT BE USED
42"
LENGTH IS
TO PREVENT DAMAGE TO THE UNIT
IS RECOMMENDED
Provisions for forks have been included in the unit base frame. No
other fork locations are approved.
T
O PREVENT POSSIBLE EQUIPMENT DAMAGE, PROPERTY DAMAGE, PERSONAL
INJURY OR DEATH, THE FOLLOWING BULLET POINTS MUST BE OBSERVED
WHEN INSTALLING THE UNIT.
• Unit must be lifted by the four lifting holes located at the
.
base frame corners.
• Lifting cables should be attached to the unit with shackles.
5
REMOVE
COVERS
17"
7 3/8"
RETURN
SUPPLY

RIGGING DETAILS

WARNING
CAUTION
,
THE FORK HOLES ON THE
.
WARNING
11"
4 7/8""
25"
T
O FACILITATE
. M
INIMUM FORK
;
, 48"
HOWEVER