Open Processor with Trane Drivers
PRODUCT DESCRIPTION
Each Open Processor (Figure 1) contains the main
processor, memory, and communications circuitry
for connecting the System 600 APOGEE to the
Trane Tracer Summit BCU.
Figure 1. Open Processor: Front View.
The Open Processor attaches to the left mounting
rail, the M-BUS rails, and the C-BUS slot of the MBC
or RBC enclosure.
N N N N O O O O T T T T E E E E : : : :
An MBC or RBC enclosure is FCC-
approved for a maximum of four Controller
Modules and/or Pre-APOGEE Open
Processors, or a maximum of five
APOGEE Open Processors.
PRODUCT NUMBERS
565-363
Open Processor with Trane Driver
(APOGEE)
565-302
Open Processor with Trane Driver
(Pre-APOGEE)
538-670
Trunk Interface II, 115V
538-675
Trunk Interface II, 230V
545-710
Battery Replacement Kit. Refer to

Installation Instructions 545-408.

545-712
MMI Extension Cable. Refer to
Installation Instructions 545-407.
538-583
Grounding Wire.
EXPECTED INSTALLATION TIMES
7 minutes.
Siemens Building Technologies, Inc.
Installation Instructions
REQUIRED TOOLS AND MATERIALS
Flat-blade screwdriver (1/8" blade width)
Wire strippers
One 115V or 230V (depending on device)
receptacle to power the Trunk Interface II
Cabling and connectors (Figure 6)
CAU U U U T T T T I I I I O O O O N N N N : : : :
CA
CA
CA
Always wear an electro-static
discharge wrist strip and discharge
accumulated static before touching
field panel components.
PREREQUISITES
MBC or RBC enclosure mounted with at
least one open slot on the C-BUS and AC
power connected.
Backups made of the current database for
all Open Processors and other Controller
Modules in the enclosure.
Both systems installed and checked out by
certified representatives of the companies
that installed each system. These checkouts
must confirm that each system is operating
and ready to communicate with the other
system.
Building level network (BLN) cable, if used,
fed into the MBC or RBC enclosure. If
necessary, splice in a connector for the
Open Processor. (Connecting this cable is
done later during start-up.)
INSTRUCTIONS
Preparing to Install the Open Processor
1.
Prepare the MBC or RBC enclosure for
shutdown by performing the following steps:
CAU U U U T T T T I I I I O O O O N N N N : : : :
CA
CA
CA
Do not install or remove an Open
Processor while the MBC or RBC
enclosure is powered up. Doing so may
damage the Open Processor or other
modules in the enclosure.
Document No. 565-939
Rev. 1, November, 1999
Page 1 of 4

Advertisement

loading

Summary of Contents for Siemens System 600 APOGEE

  • Page 1: Installation Instructions

    Each Open Processor (Figure 1) contains the main • Wire strippers processor, memory, and communications circuitry • for connecting the System 600 APOGEE to the One 115V or 230V (depending on device) Trane Tracer Summit BCU. receptacle to power the Trunk Interface II •...
  • Page 2 N N N N O O O O T T T T E E E E : : : : The goal of this procedure is to place the Open Processor’s C-BUS and M-BUS connectors into their respective slots and secure the module. Page 2 of 4 Siemens Building Technologies, Inc.
  • Page 3 Document No. 565-939 Installation Instructions Rev. 1, November, 1999 Figure 4. Attaching the Open Processor to the Mounting Guides. Figure 5. Latching the Open Processor. Page 3 of 4 Siemens Building Technologies, Inc.
  • Page 4 Trane System. Information in this publication is based on current specifications. The company reserves the right to make changes in specifications and models as design improvements are introduced. © 1999 Siemens Building Technologies, Inc. Siemens Building Technologies, Inc. Document No. 565-939.