2. Follow all of the procedures and safety precautions in the
generator Owner's Manual when installing the battery.
Verify the switch is in the off position. When preparing for
operational testing, DO NOT connect the battery until transfer
switch connections are complete.
WIRING
ERROR?
Yes
CORRECT
WIRING ERROR
12
POWER UP
UTILITY
CONNECTED?
Yes
No
SELF TEST
OK
3. Battery Power-up: Interconnect system self test feature
checks for the presence of utility voltage on the DC circuits at
the control panel terminal blocks (see flow chart).

OPERATIONAL TESTING

No
WIRING
ERROR?
No
CONNECT UTILITY
ESCAPE
PRESSED?
NO UTILITY
DETECTED
DELAY 3S
WIRING MAY BE
UNSAFE
DELAY 3S
RUN NORMAL
CODE
Yes
CORRECT
WIRING ERROR
No
ESCAPE
PRESSED?
UNABLE TO PERFORM
WIRING TEST
DELAY 5S

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 7 kW NG and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents