9.3 Commissioning Steps

NOTE
-
Commissioning can only be performed with the Honeywell S7999D 1006 color touch screen display
-
All units are fully factory tested, due to varying field conditions, boiler must be tested on final site for safety
shutdown, operation, and combustion limits.
-
The display maybe in a screen saver mode or in the home position (Sola control icon)
1.
Start main screen touch the Sola control, this will bring you to the Operation Overview window.
2.
Touch the diagnostics button, screen changes to the I/O Status window
62