6.2 INSTALLATION SITE REQUIREMENTS
The site for installation should meet the following requirements:
•
A maximum ambient temperature of 25 °C
•
No direct sunlight into the cooling chamber
•
A minimum distance between wall and rear of the instrument of 10-20 cm
should be guaranteed
•
A free ventilation of fresh air from underneath the instrument should be
guaranteed
6.2 INSTALLATION
For opening the chamber push the window to the top.
Remove the transport security underneath the specimen holder and position the waste
tray.
After installation, wait at least 4 hours before switching the instrument
on. Failure to comply may result in severe damage to the instrument.