Installation Transportation and unpacking, W365H, W375H, W3105H The machine is delivered complete with expan- sion bolts etc. packed inside the machine in the drum. The machine is delivered bolted onto the trans- port pallet and packed in a crate or box.
Page 10
Installation Transportation and unpacking, W3130H, W3180H, W3240H, W3300H The machine is delivered complete with expan- sion bolts etc. packed inside the machine in the drum. The machine is delivered bolted onto the trans- port pallet and packed in a crate or box. •...
Installation Siting and floor Install the machine close to a floor drain or open drain. In order to make installation and servicing the Fig. machine easier the following clearances are recommended: • At least 500 mm between the machine and the wall behind •...
Installation Water connections All intake connections to the machine are to be fitted with manual shut-off valves and filters, to facilitate installation and servicing. Water pipes and hoses should be flushed clean before installation. After installation hoses should hang in gentle arcs. All connectors present on the machine must be connected up.
Page 16
Installation Water type Water connection cold cold Fig. cold and Fig. cold W365H, cold and Fig. W375H/N, cold cold*/ W385N/M 5336 * For detergent container. ** Only machine with Clarus Control. Extra water valve which can be used for hard water if soft water is connected to 1.
Installation Drain connection Connect a 75 mm (3") (alt. 50 mm, 2" and only W365-W3105) pipe or rubber hose to the machine’s drain pipe, ensuring a downward flow from the machine. Avoid sharp bends which may prevent proper draining. The drainage pipe should be located over a floor Fig.
Installation Steam connection The steam supply to the machine should be fitted with manual shut-off valves and filters to facilitate installation and servicing. The connection hose must be of type ISO/1307- 1983 or equivalent. Connection size at filter: DN 15 (BSP 1/2"). Steam pressure required: 5861 •...
Installation Connection of external liquid supplies Electrical installation must be carried out by an authorized personnel! All optional equipment connected must be EMC-approved to EN 50081-1 or EN 50082-2. Distribution card A can be used to control Fig. external functions, output and input signals. Outputs (110-240V AC): Fig.
Page 22
Installation Outputs (110-240V AC): Fig. Only Exacta Control Card A See Payment system X72:1 0 V(common) (Door locked) X72:2 L1 (Door locked) X72:3 Liquid supply 1 (Prewash) X72:4 Liquid supply 2 (Main wash) X72:5 Liquid supply 3 (Softener) X72:6 Liquid supply 4 (Mop chemicals)* X72:7 Liquid supply 5 (Bleach) * Only for program 2M11, 2M12...
Page 23
Installation Fig. PCB (COGES) X70:1 Fig. X70:2 Available, signal when door is closed but program not started. X70:1 X70:3 Booked, opto- input (120-230V) X70:4 Booked, opto- input X70:2 PCB (Camping) Fig. X70:3 Booked, opto- input (120-230V) Fig. X70:3 X70:4 Booked, opto- input X70:4 5607 X70:3...
Page 24
Installation Electrolux Booking System Fig. X70:1 L (230V), output X70:2 N, output Fig. X70:3 Booked, opto- input X70:4 Booked, opto- input X70:1 Central Payment (France)/External start X70:2 Fig. X70:1 L (230V), output X70:3 X70:2 N, output Fig. X70:3 Start, opto- input (120-230V)
Page 25
Installation If more signals are required the machine can be Fig. equipped with a second distribution card B (only Clarus Control). Card B Outputs (200-240V AC): X75:1 0 V (common) X75:2 Liquid supply 5 X75:3 Liquid supply 6 X75:4 Liquid supply 7 X75:5 Liquid supply 8 X76:1...
Installation Electrical installation Electrical installation must be carried out by an authorized personnel! 1NAC Machines with frequency-controlled motors can be incompatible with certain types of earth leakage circuit breaker. It is important to know that the machines are designed to provide a high level of personal safety, which is why items of external equipment such as earth leakage circuit breakers 5332...
Page 28
Installation Three-phase connection: Connect the earth, neutral and phase wires as Fig. shown in example ”3AC” and ”3N AC” in the figure. When the installation is completed, check: • that the drum is empty. • that the machine operates by turning on the mains switch, starting the machine and using RAPID ADVANCE to reach the spin cycle (see operations manual). IMPORTANT 5333 415V 3AC machines can be supplied with Fig. 380, 400 or 415V. 240V 1AC machines can be supplied with 220, 230 or 240V. In the machine there is a transformer (not on models with Classic control) placed in the front control unit (under the top cover).
Page 29
Installation W365H Heating Voltage Total Fuse alternative alternative No heating 200 V 3 AC or Steam heating 208-240 V AC El heating 200 V 3 AC 5.6 220-240 V AC 2.2 220-240 V AC 3.2 230/240 V AC 4.4 220-240 V AC 7.3 220-240 V 3 AC 3.2 220-240 V 3 AC 7.3 240 V AC 5.4 230/240 V 3 AC 4.4 230/240 V 3 AC 5.8 380-45 V 3/3N AC 3.2 400/45 V 3/3N AC 4.4 380/400/45 V 3/3N AC 5.8 380-45 V 3/3N AC 7.3...
Page 30
Installation W375H Heating Voltage Total Fuse alternative alternative No heating 00-20 V AC . or Steam 200 V 3 AC . heating 208-240 V AC . El heating 200 V 3 AC 5.6 220-240 V AC 2.3 220-240 V AC 3.2 230/240 V AC 4.4 240 V AC 5.4 220-240 V AC 5.4 220-240 V AC 7.4 220-240 V 3 AC 3.2 230/240 V 3 AC 4.4 220-240 V 3 AC 5.4 220-230 V 3 AC 7.0 220-240 V 3 AC 7.4 380-45 V 3/3N AC...
Page 31
Installation W3105H Heating Voltage Total Fuse alternative alternative No heating 200 V 3 AC .3 or Steam 208-240 V AC .3 heating 200 V 3 AC 5.6 El heating 220-240 V 3 AC 3.2 240 V AC 5.5 240 V AC 230/240 V AC 5.3 220-240 V AC 7.4 220-240 V AC 9.7 220-240 V 3 AC 3.2 230/240 V 3 AC 5.3 220-240 V 3 AC 7.4 208-240 V 3 AC 9.2 220-240 V 3 AC 9.7 380-45 V 3/3N AC 3.2 400-45 V 3/3N AC 5.3...
Page 32
Installation W3130H Heating Voltage Total Fuse alternative alternative No heating 200 V 3 AC .3 or Steam heating 208-240 V AC .6 El heating 200 V 3 AC 9.5 220-240 V AC 2.5 208-240 V 3 AC .8 220-240 V 3 AC 2.5 380-45 V 3N/3 AC 2.5 45 V 3N AC 2.5 440/480 V 3 AC 3.5 380-45/220-240 V 3N/3 2.5 20/35 438 9143-81/09...
Page 33
Installation W3180H Heating Voltage Total Fuse alternative alternative No heating 200 V 3 AC 2.3 or Steam 208-240 V AC 2.3 heating El heating 240 V AC 2.9 200 V 3 AC 3.4 220-240 V 3 AC . 220-240 V 3 AC 7.5 380-45 V 3N/3 AC 7.5 440/480 V 3 AC 8.9 380-45/220-240 V 3N/3 AC 7.5 35/50 380-45/220-240 V 3N/3 AC . 35/50 45/240 V 3N/3/ 8.9/2.9 35/63 W3240H Heating Voltage Total Fuse alternative...
Page 34
Installation W3300H Heating Voltage Total Fuse alternative alternative No heating 200 V 3 AC 2. or Steam 208-240 V AC 2. heating El heating 240 V AC 4.3 200 V 3 AC 5.6 220-230 V 3 AC 9.4 220-230 V 3 AC 3.3 240 V 3 AC 4.3 240 V 3 AC 20.9 380-400 V 3N AC 3.3 380-400 V 3/3N AC 9.4 45 V 3N AC 4.3 45 V 3N AC 20.9 440 V 3 AC 22.2 480 V 3 AC 380-400/220-230 V 3N/3 AC 9.4 35/63 45/240 V 3N/3 20.9...
Page 35
Installation How to convert heating elements from 3AC to 1 AC (400-415V 3AC to 230-240V 1AC) on W365H, W375H and W3105H. • Take off isolator cover plate and front panel to expose heating elements. Fig. • Remove the cables A. 400-45V 3AC �� �� �� 5835 • Take off wire L3 (A) from terminal L3 on isolator Q and from terminal 6 Fig. on heating relay K2. Take off wire L2 (B) from terminal L2 on isolator Q and reconnect it to terminal N (neutral) instead. • The heating elements have coloured insulators on the tips, ine is red, the other is white.
Function checks 10:1 Function checks, Exacta Perform the following checks once the machine is installed: • Open the manual water valves. • Turn on the power at the external switch. • Put detergent into compartment 2. • Choose a high-temperature program. Fig.
Page 38
Function checks 10:2 Function checks, Clarus Control Manual operation • Switch on the machine's main switch. • Open the manual valves for water and for steam if the machine has steam heating. In the operating manual, chapter "Manual operation", one can find how to operate the machine manually.