Section 4
Starting up
4.8
4.9
50

Checking VT circuits

Check that the wiring is in strict accordance with the supplied connection diagram.
Correct possible errors before continuing to test the circuitry.
Test the circuitry.
Polarity check when applicable; this test is often omitted for CVTs
VT circuit voltage measurement (primary injection test)
Earthing check
Phase relationship
Insulation resistance check
The primary injection test verifies the VT ratio and the wiring all the way from the
primary system to the IED. Injection must be performed for each phase-to-neutral
circuit.
While testing VT secondary circuit and associated secondary
equipment, care shall be exercised to isolate the VT from the circuit
being tested to avoid backcharging the VT from the secondary side.

Using the RTXP test switch

The RTXP test switch is designed to provide the means of safe testing of the IED. This
is achieved by the electromechanical design of the test switch and test plug handle.
When the test plug handle is inserted, it first blocks the trip and alarm circuits then it
short circuits the CT secondary circuit and opens the VT secondary circuits making
the IED available for secondary injection.
When pulled out, the test handle is mechanically stopped in half withdrawn position.
In this position, the current and voltage enter the protection, but the alarm and trip
circuits are still isolated and the IED is in test mode. Before removing the test handle,
check the measured values in the IED.
Not until the test handle is completely removed, the trip and alarm circuits are restored
for operation.
1MRK 511 360-UEN A