Quick Reference Guide for Viper FCB and FUB Units
Electrical Requirements:
Wiring:
Minimum Clearance Requirements:
Water Requirements:
CO
Requirements (2 regulators):
2
Syrup Tubing Requirements:
Before attempting to install or service this machine,
Page 1
Viper FCB/FUB Quick Reference Guide
read this Quick Reference Guide!
For more detail, refer to manuals supplied with the unit.
For Technical Service: 1-800-238-3600 (US); www.cornelius.com (Global)
215-245 VAC, 60 Hz supply voltage
2-Barrel: NEMAL6-20P Dedicated 20 Amp Circuit Required
3-Barrel: NEMA L6-30P Dedicated 30 Amp Circuit Required
4-Barrel: NEMA L6-30P Dedicated 30 Amp Circuit Required
NOTE: If voltage is less than 215 VAC or more than 245 VAC, then a Buck/Boost
transformer must be installed
All connections and wiring must comply with state and local codes.
Condenser air discharge is from the top of the unit. A minimum of 18 inches
clearance is required.
Cold air intake clearance is 2 inches on the sides of the unit or 2 inches in back.
25 psig flowing through 1/2" i.d. water supply line.
2 and 3-Barrels: At a volume of 100 GPH.
4-Barrel: At a volume of 150 GPH.
NOTE: If water requirements are less than minimum, then a water booster must
be installed. If water pressure is greater than 100 psig static, then a water regula-
tor must be installed
1 dedicated regulator set to 75 psig for pump supply located within six feet of
machine.
1 dedicated regulator set to 70 psig for FUB or 75 psig for FCB.
Most syrups use 3/8" inside diameter tubing up to 75 feet. 1/2" inside diameter
tubing is required for greater distances.
For FUB units, the length of tubing runs must not exceed 100 ft. horizontally and 10
ft. of vertical lift.
NOTE: High viscosity syrups require 1/2" inside diameter tubing for all distances.
June 8, 2012
620055004QRG
Rev. A