Use a suitable container to catch the fuel that
will spill during system bleeding process. Clean
up all spilled fuel after bleeding.
2.9.1.3 Generator Set Lubrication
Check the engine crankcase oil level before operating
and add oil to the proper level – the dipstick "FULL "
mark. Never operate the engine with the oil level
below the dipstick "ADD" mark. See "Specifications"
and "Engine Oil Recommendations" sections.
This engine is shipped from the manufacturer
with 15W-40 oil. This oil should be changed after
30 hours of operation.
2.9.1.4 Engine Coolant
Have the engine cooling system properly filled with
the recommended coolant mixture. Check the system
for leaks and other problems. See the "Specifications"
and "Coolant" sections.
2.9.1.5 Belt Tension
Check-the engine-fan belt tension and condition prior
to placing the unit into service and at recommended
intervals. Belt tension is correct when a force of
approximately 22 pounds (10 kg), applied midway
between pulleys, deflects the belt about 3/8- to 5/8-
inch (10 to 16 mm).
2.9.1.6 Electrical System
Make sure the generator is properly connected to an
approved earth ground.
Make sure the generator battery is fully charged,
properly installed and interconnected, and ready for
use.
Check to ensure that there are no loose electrical con-
nections. Restrain any loose wires to keep them clear
of any moving generator set components.
2.9.1.7 Rodent Protection
Make sure the four, three-inch diameter cap plugs
(part # 0A8785) are properly installed in the tie-
down holes in the side rails of the unit's base frame
(Figure 2.4). The cap plugs are shipped in a plastic
bag located in the lower connection box. These plugs
are needed to prevent rodents from accessing the
interior of the generator set. On acoustic units, cap
plugs also are needed to stay within noise specifica-
tion limits.
NOTE:
Section 3 – Operation
Standby Generator Set
Figure 2.4 – Base Frame Cap Plugs

2.9.2 START-UP INSPECTION

A standard three-part form titled "Start-up Inspection
for Standby Power Systems" (part # 067377) should
be completed by an Authorized Service Dealer. As
stated on the form, inspections are to be complet-
ed only by factory-trained personnel. The installer
should complete the form and disperse copies as
follows:
• White copy: Mail to Generac Warranty Department,
P .O. Box 8, Waukesha, WI 53187.
• Pink Copy: For service file of installing dealer.
• Yellow Copy: For the customer's records.
3.1
GENERATOR CONTROL AND
OPERATION
Refer to the appropriate control panel operator's
manual for this unit.
3.2
OPERATING UNIT WITH
AUTOMATIC TRANSFER SWITCH
If the generator has been installed along with an auto-
matic transfer switch, such as a GTS-type switch, the
engine may be started and stopped automatically or
manually.
Refer to the applicable manual for the trans-
fer switch and to "Transfer Switch Start Signal
Connections" section. In addition, please note the
dangers under "Engine Start-up and Transfer."