9.7 Complete Start Up Procedure

1.
Reset control parameters to operating settings if
adjusted to allow startup and operation test.
2.
Follow instructions TO TURN OFF GAS TO APPLIANCE
(page 42) if boiler is not being placed into
immediate operation.
3.
Enter installer information on Warranty Registration
Card.
4.
Gather all instructions, manuals, wiring diagrams,
warranty registration card and other supporting
information. Review with user and/or affi x in
conspicuous location adjacent to boiler.